September 7, 200421 yr I need to track stages of a project. For each step, I have a "completed by" field and a "completed on" field. When a person enters their initials in the "completed by" field I want the date to auto enter in the "completed on" field. I can't figure out the calculation. I searched the archives but didn't find an answer. Thanks in advance for your help!
September 7, 200421 yr I think Case( completed_by; Get(CurrentDate) ) should work. Make sure it's stored.
September 7, 200421 yr Author Still not working. FM will accept the calculation, but when I enter info into the "completed by" field, nothing appears in the "date completed" field. Any other ideas?
September 7, 200421 yr Sorry, I should have said Case( not IsEmpty(completed_by); Get(CurrentDate) ).